|
|
|||||||||||||||||||||||||||||||||||||||
| MULTIPLE APPLICATION RE-INJECTION SYSTEM |
|||||||||||||||||||||||||||||||||||||||
![]() MARS: How it Works The Multiple Application Re-injection System or MARS enables any process to be fitted to any well at any time. This is achieved by establishing a retrofit coaxial access port which has been compared to “a USB port” for a wellhead. Unplanned maintenance therefore no longer requires major field shutdowns or infrastructure decommissioning; access is simply achieved via the “USB port”. This technology delivers a low cost and flexible field development strategy for new and existing oil fields. MARS: What it Enables The challenge to facing Operators can be summarised as follows: • To maximise the NPV of assets
These seemingly diverging challenges can be made to converge when you begin to realise the range of production optimisation opportunities realised by literally installing “any process on any well”. The technologies and the range of possible solutions enabled by MARS are constantly evolving. The number of existing or emerging processing technologies that can be fitted on to any wellhead with minimal risk includes:
MARS: Projects BP KING, Gulf of Mexico, MARS enabled Multiphase Pumping • the first Subsea Multiphase Pump in the Gulf of Mexico In the KING project, MARS offered BP a low risk method of gaining access to their wellstream. This was achieved without breaking into the existing flowline system and additionally minimizing well downtime. Each of the two pumps were installed on separate foundations adjacent to the existing wellheads. The MARS system was installed onto a “Universal Work Platform” or UWP which in turn presented two vertical CVC hubs to enable jumpers to be installed from pump to tree.
In addition to using MARS, BP also selected DES’ proprietary POSSibilties (Production Optimisation Simulation Software) to evaluate various enhanced recovery opportunities. Working closely with the BP reservoir team to establish a base case production profile, the software was able to run multiple parallel simulations to quickly screen various artificial lift solutions. It subsequently compared various different pumping technologies performance throughout the life of field to determine the optimum pump type, size and location. DES were fully integrated into the BP delivery team throughout their ‘CVP’ process providing expertise and resource for:
• Preliminary screening
SHELL BITTERN, UK North Sea, MARS enabled Reservoir Stimulation
• Remote ROV subsea operations Two systems are being retrofitted subsea onto existing hardware while the third system will be installed onto the next operational Xmas tree during SIT. The MARS assembly with modified choke effectively gave the Operator a safe access into the reservoir and pipeline system.
TOTAL MEDIDOR, Angola, Subsea multiphase metering and allocation sampling package in West Africa In 2008, Total will install their first MARS enabled multiphase metering/sampling package as part of the Medidor project in West Africa. The challenges facing the team were significant:
• Install on operational field - 1400m water Working with both choke and xmas tree manufacturers DES were able supply a complete MARS solution onto subsea hardware in situ which had not been specifically designed for maintenance or for retrofitting processing solutions. By providing continuous 24/7 multiphase metering capability, Total will increase ultimate recovery from the reservoir through optimised management of individual wells. The MARS method in this case has several advantages over existing traditional installation methodologies, including:
• MARS uses tree installed double barriers to isolate well & flowline
In addition, meter operation and accuracy is optimised due to:
• Meter installed upstream or downstream of the choke to optimise accuracy MARS: Brochure Download |
|||||||||||||||||||||||||||||||||||||||